Steel Pipe Sheet Pile – Work Method

Dear practical constructions, Civil engineers, Civil students or even just blog reader.

Here is below, I will explain briefly work method of Steel pipe sheet pile driving, based on my experienced in previous project. I know specially for Civil student that have no experience in construction will have a benefit by reading the work method below.

I will explain the work method by sketches, instead of by many words, as we know that one sketch can explain dozen of words. The key is how we can gain the information and knowing sequences of work of steel pipe sheet pile driving. as shown on the sketches, we also know that is needed pile guide as temporary works, etc. Please see in figures below the work method sketches.

Note: (Step A is bottom part, Step B is the top part by on site splicing), bear in mind that is needed  one pile as a master pile; means bottom part and top part should be finished before next pile to be continued, as shown on figure Step-A1 and Step-A2.

You also should know that there are three common types joints of steel pipe piles (L-T type, P-P type and P-T type) as shown on figure below:

SPSP Juctions Type

SPSP Joint Types.

SPSP-work wethod (1)
SPSP-work wethod (1)
SPSP-work wethod (1)
SPSP-work wethod (1)
SPSP-work wethod (1)
SPSP-work wethod (1)
SPSP-work wethod (1)
SPSP-work wethod (1)
SPSP-work wethod (1)
SPSP-work wethod (1)
SPSP-work wethod (1)
SPSP-work wethod (1)
SPSP-work wethod (1)
SPSP-work wethod (1)
SPSP-work wethod (1)
SPSP-work wethod (1)


Responses

  1. thank you,..hope you gain new knowledge.

  2. Kalo yang satu ini, bukan ngejawabnya yang susah, melainkan memahami pertanyaannya yang susah, saya tidak tahu mengambil pertanyaannya dimana?,…sorry, just joke.

  3. Thanks pak Ainul,
    berhubung karena harga minyak dunia lagi anjlok, sehingga banyak project yang di pending dan banya tender bahkan di cancelled, sehingga saat ini kesibukan agak berkurang dan sekarang punya waktu untuk nge-blog kembali.
    anyway thank you.

  4. akhirnya posting lagi… salam pak. saya yang kemarin ketemu di edgen murrays seminar

  5. Pak Sinaga,
    I appreciate your generousity to let others,specially young engineers to share your knowledge and experiences.

  6. pa sinaga bisa minta bantu, kalau kita bikin perencanaan pelabuhan pake spun pile dengan jarak tiang ke tiang 3 meter, memakai ponton laut/ sungai analisnya mengambil dimana

  7. sangat membantu saya untuk seorang engineer


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Categories

%d bloggers like this: